Durkan Ltd won a £126m contract with Peabody to design and build 404 new homes. CCS was contracted to undertake 1st and 2nd fix carpentry and joinery package with certified fire door installation.
Project duration: 18 months
CCS Package Value: £3.3 million
Durkan Ltd won a £45m contract with Peabody to design and build 130 new homes. CCS was contracted to undertake 1st and 2nd fix carpentry and joinery package with certified fire door installation.
Project duration: 12 months
CCS Package Value: £1.9 million
Durkan Ltd won a £100m contract to construct 354 flats across 4 blocks.
CCS was contracted to undertake 1st and 2nd fix carpentry and joinery package with certified fire door installation.
Project duration: 18 months
CCS Package Value: £1.7 million
Kier London won a £56m state-of-the-art new academic studio and research building located at its South Campus.
CCS was contracted to undertake 1st and 2nd fix carpentry works with certified fire door installation.
Project Duration: 8 months
CCS package Value: £1.2 million
Galiford Try Ltd won a £60m contract to construct a retirement village of 210 apartments across 6 blocks.
CCS was contracted to undertake all structural carpentry works.
Project Duration: 12 months
CCS Package Value: £855,000
Durkan Ltd won an £8m contract with Peabody to design and build a library. CCS was contracted to undertake 1st and 2nd fix carpentry and joinery package with certified fire door installation.
Project duration: 4 months
CCS Package Value: £420,000
Morgan Sindall won £8m contract to construct a three story home for innovation in Southend-on-Sea.
CCS was contracted to undertake first and 2nd fix carpentry and joinery package with certified fire door install.
Project Duration: 4 months
CCS Package Value: £216,500
Kier London won a £26m contract to build a new state of the art secondary school for Camden council.
CCS was contracted to undertake all 1st and 2nd fix carpentry works with certified fire door installation.
Project Duration: 28 weeks
CCS package Value: £190,000
Kier won a £13.6m contract to construct a special educational needs (SEN) school in New Addington.
CCS was contracted to undertake first and 2nd fix carpentry and joinery package with certified fire door install.
Project Duration: 4 months
CCS Package Value: £136,000
ISG Construction won a 5m contract to construct a new build SEND school in Witham, Essex.
CCS was contracted to undertake 1st and 2nd fix carpentry and joinery package with certified fire door install.
Project Duration: 4 months
CCS Package Value: £115,000
Kier won £25m contract to refurbish the Italian hospital into a new Sight and Sound Centre within a grade II listed building.
CCS was contracted to undertake 1st and 2nd fix carpentry and joinery package with certified fire door install.
Project Duration: 6 months
CCS Package Value: £344,000
Vinci Building Solutions won contract to replace and upgrade the fire doors throughout the prison.
CCS was contracted to undertake certified fire door install.
Project Duration: 6 months
CCS Package Value: £500,000
Fileturn won £12.2m contract to undertake a large redevelopment project for this DoubleTree hotel, creating 74 additional bedrooms.
CCS was contracted to undertake 1st and 2nd fix carpentry and joinery package with certified fire door install.
Project Duration: 9 months
Package Value: £425,000
Knight Harwood won contract to construct a nine-storey building to house the Library and Archive of the Church of England.
CCS was contracted to undertake 1st fix structural carpentry.
Project Duration: 3 months
Package Value: £110,000
Kier London won a £8m contract to undertake all refurbishment works to turn a run down school into a purpose built school for student's with autism in Haringey. CCS was contracted to undertake all 1st and 2nd fix carpentry works including certified fire door install.
Project Duration: 20 weeks
Package Value: £130,000
Kier won a £32m contract to construct a new school for girls in Thamesmead , the schools is expected to house 2500 new students across 4 blocks and 3 levels.
CCS was contracted to undertake all 1st and 2nd fix carpentry including certified fire door install.
Project Duration: 35 weeks
Package Value: £245,000
Durkans Ltd won a £70m contract to construct a mixture of 180 new build and refurbishments of grade 1 listed army barracks into apartments and houses.
CCS was contracted to undertake all 1st fix structural works and 2nd fix works with certified fire door installation.
Project Duration: 24 months
CCS Package Value: £2.9 million
Kier London won a £17m contract to undertake all refurbishment works to a block of 7 floors of commercial units.
CCS was contracted to undertake all 1st and 2nd fix carpentry works with certified fire door installation.
Project Duration: 25 weeks
CCS Package Value: £348,000
Kier London won a £43m contract to undertake all refurbishment works to the existing Medway Lodge building. Turning a run down building in to into a fit for purpose mental health institute.
CCS was contracted to undertake all 1st and 2nd fix carpentry with certified fire door installation.
Project Duration: 45 weeks
CCS Package Value: £350,000
Kier London won a £16m contract to construct a new extension to the Ilford boys school to take more pupils.
CCS was contracted to undertake all first and 2nd fix carpentry and joinery works with fire door installation.
Project Duration: 24 weeks
CCS Package Value; £100,000
Interserve Construction won £110m contract to design and construct a new prison within the Belmarsh prison campus in Woolwich, East London.
CCS was contracted to undertake the fitting of the cell furniture and FFE.
Project Duration: 65 weeks
CCS Package Value: £520,000
Interserve Construction won £20m contract. The project comprises the construction of a new build Young Offenders' Institution comprising a 180-person Housing Block and an Education Block. The project is located adjacent to the existing Cookham Wood prison.
CCS was contracted to undertake the internal joinery including timber doorsets, timber glazed screens, ironmongery, bespoke joinery, IPS systems, fitting of cell furniture and FFE.
Project Duration: 52 weeks
CCS Package Value: £700,000
Interserve Construction won £27m contract to design and construct an extension to the existing Immigration Return Centre.
CCS was contracted to undertake the internal joinery including timber doorsets, timber glazed screens, ironmongery, bespoke joinery, IPS systems, fitting of cell furniture and FFE.
Project Duration: 35 weeks
CCS Package Value: £225,000
Interserve Construction won £46m contract to design and construct a new Immigration Return Centre within the grounds of Gatwick Airport.
CCS was contracted to undertake the internal joinery including timber doorsets, timber glazed screens, ironmongery, bespoke joinery and IPS systems.
Project Duration: 32 weeks
CCS Package Value: £280,000
Interserve Construction won £21.6m contract to construct and design a new air despatch facility for 47 Air Despatch, Royal Logistics Corps, at RAF Brize Norton.
CCS was contracted to undertake the internal joinery including timber doorsets, timber glazed screens, ironmongery, bespoke joinery, IPS systems and FFE.
Project Duration: 20 weeks
CCS Package Value: £180,000
Interserve Construction won £18m contract to construct and design 42no. new houses within the grounds of the RAF base, comprising of 9no. 4 bedroom detached properties and 33no. semi-detached properties.
CCS was contracted to undertake the structural joinery and internal joinery including, joisting, trussed roofs, stairs, timber doorsets, ironmongery and kitchens.
Project Duration: 32 weeks
CCS Package Value: £460,000
Interserve Construction won £6m contract to refurbish 96no. bedrooms and communal washrooms.
CCS was contracted to undertake the internal joinery including timber doorsets, ironmongery, bespoke joinery, IPS systems and FFE.
Project Duration: 25 weeks
CCS Package Value: £160,000
Interserve Construction won £8m contract to refurbish 106no. bedrooms and extension to sergeants mess.
CCS was contracted to undertake the structural joinery and internal joinery including, roof trusses, joists, timber doorsets, ironmongery and kitchens.
Project Duration: 35 weeks
CCS Package Value: £320,000
Interserve Construction won £12m contract to refurbish 76no. dorms, shower blocks and construct a new six form house block.
CCS was contracted to undertake the structural joinery and internal joinery including, roof trusses, joists, cladding, timber doorsets, ironmongery and kitchens.
Project Duration: 52 weeks
CCS Package Value: £420,000
Durkans ltd won £19m contract to design and build a combination of 80 apartments and houses.
CCS was contracted to undertake all 1st and 2nd fix carpentry works with certified fire door installation.
Project Duration: 45 weeks
CCS Package Value: £357,000
Durkan ltd won £7m contract to construct 31no. new properties
CCS was contracted to undertake the structural joinery and internal joinery including, joists, glazed screens, timber doorsets, ironmongery and kitchens.
Project Duration: 35 weeks
CCS Package Value: £220,000
Morgan Sindall won £422m contract from Thames Water, which stretches for seven kilometres 90 metres below London and features some of the deepest shafts in Europe. Built as part of the MVB joint venture, the tunnel will improve water quality in the River Lee by intercepting a combined sewer overflow at Abbey Mills Pumping Station, Stratford
CCS was contracted to undertake the structural joinery and internal joinery including, joists, glazed screens, timber doorsets, ironmongery and kitchens.
Project Duration: 60 weeks
CCS Package Value: £600,000
Knight Harwood won the contract to build a new spa within the basement of the current hotel building.
CCS was contracted to undertake certified fire door installation and IPS ducting.
Project duration: 5 weeks
CCS Project Value: £45,000
Lengards won the contract to undertake all refurbishment works to an existing fire station and change into a modern art gallery.
CCS was contracted to undertake all 1st and 2nd fix carpentry works.
Project Duration: 30 weeks
CCS package Value: £97,000
Lengard won £5m contract to construct a new community centre.
CCS was contracted to undertake the structural joinery and internal joinery including, roof trusses, joists, cladding, timber doorsets, ironmongery and kitchens.
Project duration: 18 weeks
CCS Package value: £120,000
Lengard won £12m contract to construct an extension to the existing school and refurbish the school hall.
CCS was contracted to undertake the structural joinery and internal joinery including, roof trusses, joists, glazed screens, timber doorsets, ironmongery and kitchens.
Project duration: 34 weeks
Package value: £280,000
Lengard won £7m contract to construct an extension to the existing school phase 2.
CCS was contracted to undertake the structural joinery and internal joinery including, roof trusses, joists, glazed screens, timber doorsets, ironmongery and kitchens.
Project duration: 24 weeks
CCS Package value: £180,000
Lengard won £16m contract to construct an extension to the existing school.
CCS was contracted to undertake the structural joinery and internal joinery including, roof trusses, joists, glazed screens, timber doorsets, ironmongery and kitchens.
Project duration: 40 weeks
CCS Package value: £380,000
Lengard won £6m contract to construct a new-build community centre.
CCS was contracted to undertake the structural joinery and internal joinery including, joists, glazed screens, timber doorsets, ironmongery and kitchens.
Project duration: 16 weeks
CCS Package value: £80,000
Copyright © 2018 Comprehensive Carpentry Services - All Rights Reserved.
Powered by GoDaddy Website Builder